How Long Does Renovation Take in Singapore?

General Renovation Duration Singapore

Renovating your home in Singapore is exciting — but it can also test your patience! One of the most common questions we get at Earth Interior is: "How long will the renovation take?" The truth? It depends on the scope, permits, and type of property.

Here’s your ultimate breakdown by project type.


General Renovation Timeline in Singapore

Singapore Renovation Timeline Table

For most projects, here’s a rough guide:

  • Minor works (painting, light carpentry): 2–4 weeks
  • Partial renovation (kitchen, bathroom): 4–8 weeks
  • Full renovation (entire home): 8–14 weeks
  • Major overhaul (structural, hacking): 12–16 weeks

Actual duration depends on project complexity, permit approvals, and customization needs.


How Long Does a BTO Renovation Take?

BTO Renovation Duration Singapore

For brand new BTO flats:

  • Basic renovation: 6–8 weeks
  • Extensive custom works (feature walls, built-ins): 8–12 weeks

Tip: Since BTO flats come bare, carpentry and tiling work tend to take longer than resale flats.


How Long Does HDB Renovation Take?

HDB Renovation Duration Singapore

For resale HDB flats:

  • Minor renovations (painting, flooring): 4–6 weeks
  • Full home renovations (kitchen, bathroom, rewiring): 10–14 weeks

Important: All HDB renovations must comply with HDB rules and approved by an HDB-licensed contractor. HDB renovation permit typically takes 2–4 weeks to approve after submission.


How Long Does Bathroom Renovation Take?

Bathroom Renovation Duration Singapore

Bathroom-only makeovers are faster:

  • Simple upgrades (new tiles, fixtures): 2–4 weeks
  • Full bathroom remodeling (hacking, plumbing, waterproofing): 4–6 weeks

Delays often come from waterproofing works, which require drying and inspection time.


How Long Does Kitchen Renovation Take?

Kitchen Renovation Duration Singapore

Kitchen makeovers vary based on size and complexity:

  • Simple kitchen remodeling (cabinets, backsplash): 4–6 weeks
  • Full kitchen renovation (hacking, retiling, plumbing changes): 6–8 weeks

Custom carpentry and imported appliances can extend timelines.


How Long Does a Full House Renovation Take?

Full House Renovation Duration Singapore

If you’re redoing the entire home:

  • Typical 3-room or 4-room flats: 8–12 weeks
  • Larger condos or landed properties: 12–16 weeks (or more)

Scope matters. Structural changes, hacking works, and luxury material installations extend renovation time.


How Long is a Renovation Warranty in Singapore?

Renovation Warranty Duration Singapore

Most interior design firms and contractors in Singapore offer a 1-year warranty for renovation workmanship. This covers issues like cracks, peeling, water leakage, or minor defects post-renovation.

Always check the warranty terms in your renovation contract.


How Long After Renovation Can You Move In?

Move In After Renovation Singapore

You should wait at least 1–2 weeks after renovation before moving in, to allow:

  • Paint fumes to dissipate
  • Grout, adhesives, and finishes to fully cure
  • Final touch-ups or cleaning

Especially for families with young children or elderly, proper airing-out is important.


Summary: Renovation Duration at a Glance

Renovation timelines in Singapore vary based on your project scope:

  • Minor Renovations: 2–4 weeks
  • Bathroom Renovation: 2–6 weeks
  • Kitchen Renovation: 4–8 weeks
  • BTO Full Renovation: 6–12 weeks
  • HDB Resale Renovation: 4–14 weeks
  • Full Home Overhaul: 8–16 weeks

Pro Tip: Always buffer an extra 2 weeks in case of unexpected delays.


At Earth Interior, we pride ourselves on efficient project management — delivering your dream home on time, without compromising quality. Ready to start your renovation journey? Contact us today for a free consultation.